APICS The Association for Operations Management

Wichita Chapter 71

 

Advancing Productivity, Innovation, and Competitive Success

 

 

   
line

Main MenuBackNext

APICS Wichita Chapter 71 January 2008 Newsletter page 4

Article of the Month
Improving Workcenter Performance - Part II of II

Gene Brockmeier, CFPIM, CIRM Manufacturing Education & Systems, Inc

In last month’s newsletter, I wrote about a common problem in manufacturing: behind schedule work in the shop.  We looked at a brief introduction of the problems, analysis and some measurements of the process.  The workcenter was scheduled manually through much effort by the general foreman and shop lead man. Many jobs were behind schedule causing much confusion and poor operations performance.  This month’s article will focus on the assessment, root cause analysis, solutions and what contributed to the success of the project.

Much conflict existed trying to meet numerous demands to expedite orders. There was constant change to the “hot” list with multiple managers directing workers, confusion, change of direction, frustration and wasted effort.  Operations management & employees wanted a better process to manage and schedule the shear workcenter. They were open to process changes.

To resolve these problems, someone of leadership and decision making power must desire to correct the situation. A “perceived need to improve” must exist. In many situations, problems will be rooted in other organizations and you must have sufficient decision making authority to cause changes in those organizations.  Essentially, if you can’t get the process changed in another organization, your improvement effort will not go as smoothly and be as successful as you would like. Here are the findings and solutions from the project.

I initially printed off the dispatch list and compared it to the mountain of job paper in the workcenter. There were many jobs which could not be worked for any number of reasons. Those jobs were identified, put on “hold” and the paperwork returned to the production control department. At the time, the “held for” reporting process in the software wasn’t being used to identify, track and manage jobs. Prior to this we had no idea how many jobs were on hold.  We implemented a formal held-for process. We identified approximately 75 jobs that could not be worked and changed the job status to “held”. A held-job report and meeting are now in place and continually review.

Another major problem was the volume of job paper in the workcenter.  It was common to have more than 200 jobs in the workcenter. A review of the dispatch list identified jobs that weren’t scheduled to start for many months in the future.  All the jobs that weren’t scheduled to start within the next two or three months were returned to production control. A more formal release process was implemented. We added an additional operation at the beginning of the part routing for “order release” with two days of queue time. Now we have a dispatch list for the order release process. The two days of queue time is added into the schedule and production schedulers have a dispatch list to work from.

The dispatch list also revealed that there were many jobs behind schedule.  An analysis showed that some of the jobs had already been completed but the operation had not been clock complete by the machine operators. A more formal process is in place to ensure that job operations are clocked complete.

We also found that many of the leadtimes for both internal and external operations were seldom updated.  We developed and implemented an on-going review and update of internal, outside service and shipping leadtimes.  Leadtimes are reviewed when jobs are released and compared to the standard planning leadtimes and updates are made for any differences. One benefit of leadtime analysis was the identification of “batching up” of like metals for outside processing.  It is common practice to stage a number of jobs of like materials and send them all at the same time for outside processing. This helps reduce vendor minimum charges.  We inserted queue time before the vendor operation to allow time in the schedule to batch up like materials.

Another problem was ensuring that materials used on a job were reported.  A process and report has been implemented to ensure that once a job was started, that the material has been issued to the job and relieved from inventory. 

We listened to people in the shop! I had many discussions with the shop people and they had always said that there wasn’t enough time in the schedule.  Our detailed analysis found this to be true in quite a few cases.  The implementation of a lead time management process has been vital to getting jobs released to the shop in time. The analysis, identification and resolution of root causes of problems were key to success. The acceptance of new processes by employees and management also contributed to the program. Having a plan and leadership is step #1 to getting started and maintaining momentum. 

Today, operations management is making very few trips to the workcenter to sort through jobs and schedule operations. The dispatch list is being used by workcenter employees and has significantly reduced the amount of confusion and conflict in between production control, shipping and manufacturing. Behind schedule has been reduced not only in the shear workcenter but throughout the factory as jobs are getting started on time. There is much better visibility of the status of the workcenter. There has been a significant reduction in supervisory time needed to control the workcenter along with a decrease is overtime.  More work is getting done less confusion effort and we’re taking advantage of cutting jobs with like materials at the same time.

Information is a vital component in today’s manufacturing environment. Information in your computing system, will uncover the root causes of problems in your factory. I am 100% convinced of this. I worked with some very bright Dutch systems analysts in Buffalo, NY and they said “the devil is in the details”. If you can’t / don’t / won’t use your computing reports, then you’ll never advance to the next level of performance. You won’t be able to identify and fix the business processes that are creating problems. Computing system reports point the finger at the processes that are not working, identify responsibilities and processes where improvements are needed.  They identify business processes such as “lead time management” which is quite often overlooked in the manufacturing organization.

Some comments from workcenter lead & shop foreman:

“I only go over to the shear area once or twice a day, sometimes I don’t go over there at all” “Things are going great and we’ve got a good handle on it now”

We continue to measure and polish the new processes and keep people motivated to identify problems, communicate them and work with others to solve them.

apics
.
apics
Inside this issue: (1.) JANUARY PDM,  (2.) PRESIDENT'S MESSAGE  (3.) SOUTHWESTERN COLLEGE,   (4.) IMPROVING WORK CENTER PERFORMANCE,  (5.) SUBSCRIPTION INFORMATION Main Menu

Home  |  Newsletters  |  Education  |  Information  |  Contact 
© Copyright Wichita APICS 2008